According to the approved plan of brewery reconstruction the following set of works was carried out:
1) design documentation development for fermentation section expansion;
2) purchase, manufacture and supply of tank equipment, pipeline fittings, instrumentation and control equipment;
3) software development;
4) equipment installation to the design position;
5) performance of installation, installation supervision and commissioning works.
Successful completion of the 1st stage of reconstruction allowed to increase the production volume of finished goods and level of automation.