ZAVKOM-ENGINEERING LLC has completed the complete delivery of an Adhesive Preparation Plant for Synergy LLC

Within the framework of this project, the company's specialists carried out the following works: 

  1. Design;
  2. Complete supply of equipment;
  3. Supervision;
  4. Commissioning works.

Last year, at the final stage of the project, technical support was provided to:

  • Glue production unit in terms of completing installation work;
  • Water pipelines fitting;
  • Pipelines fitting for supplying urea glue to the press;
  • Installation of shut-off and control valves;
  • Valves pinout;
  • Refrigeration machine fitting;
  • Fans installation.

During the experimental production of urea-formaldehyde glue, compliance with all required quality indicators was confirmed. As for now, the product has been developed to reach its design capacity.

 

ZAVKOM-ENGINEERING LLC has completed the complete delivery of an Adhesive Preparation Plant for Synergy LLC ZAVKOM-ENGINEERING LLC has completed the complete delivery of an Adhesive Preparation Plant for Synergy LLC ZAVKOM-ENGINEERING LLC has completed the complete delivery of an Adhesive Preparation Plant for Synergy LLC