Successful start-up of distillery in Dushanbe

Projects

ZAVKOM-ENGINEERING LLC implemented a turnkey construction project for distillery with a capacity of 2,800,000 liters per year.

The investor in this project was LLC AVESTO GURUH. New production is equipped with modern equipment, allowing producing premium class of liquors.

Duaring implementation of the contract, the following works were performed:

  • Designing of a plant with a capacity of 2.8 million liters per year;
  • Supply of equipment in accordance with the completed project;
  • turnkey installation of the plant
  • Installation supervision;
  • Commissioning works.

See also

Watch projects

Expansion of Liquor and Spirits Production Facility
Completed
Expansion of Liquor and Spirits Production Facility
AVESTO GURUH LLC
Dushanbe, Tajikistan
Bottled water plant
Completed
Bottled water plant
LLC «AVESTO GURUH»
City of Dushanbe
Implemented a project for the construction of a distillery
Completed
Implemented a project for the construction of a distillery
LLC «AVESTO GURUH»
City of Dushanbe

Story