The scope of work completed under this project includes:
- Fabrication of tank/vessel equipment
- Supply of piping and interconnecting skid pipework
- Supply of control panels and instrumentation (I&C)
- Supply of cable products
Project execution is proceeding according to the approved schedule:
CURRENT STAGE: Engineering design is underway, along with equipment fabrication and procurement of components.
FOR 2026: Installation, supervision of installation, and commissioning works are scheduled at the Client's site.
The project is aimed at achieving three primary objectives:
- Increase production capacity
- Ensure stability of process parameters
- Create a foundation for further production automation