Formaldehyde resin production calculator

Calculator for selecting a formaldehyde resin production plant

Specify the type of resin, power and composition of raw materials - the calculator will calculate the approximate installation parameters.

Products and power

10 000
2
330
180

Raw materials


Additional equipment

30 t/day
Daily productivity ? Q = M / D, where M is capacity, t/year; D—working days
16 t/day
Formalin consumption ? G = Q × k, where k: CF 0.55, FF 0.40, MF 0.45
6 t/day
Urea consumption ? G = Q × k, where k: CF 0.20, MF 0.25
150 kW
Power consumption ? P = Q × p + P_main, where p ≈ 4–6 kWh/t
1.8 t/h
Steam consumption ? D = Q × s, where s ≈ 0.06–0.08 t steam per t resin
2 lines
Recommended Configuration ? Optimal: up to 5,000 t/year → 1–2, up to 15,000 → 3–4, over → 5+
* The calculation is based on industry-average indicators. Exact figures are determined after a detailed survey.